06 May 2015

further progress first roof is ready

 first roof ready
 starting landscaping
Ping Pool Villas construction 2015, 2015
The whole story and actual updates under the link above

24 February 2015

making progress - 57 days into construction - will start this week with roof construction

https://picasaweb.google.com/104211979864667748960/PingPoolVillasConstruction20152015?authuser=0&feat=directlink

more pictures of construction - click on the picture

10 February 2015

45 days into construction





05 January 2015

Just 10 Days Into Construction

I'm very happy with the process of our construction project.
It was just 10 days ago that we agreed with a team of local workers for the basic construction and immediately started with measurement for excavation.
Today all iron work for footings and for all posts for both 2-storey houses is done and they are pouring the cement into the footings at the moment (to be finished by today).
Joy is doing a very professional and effective work as "constructor", coordinating workers and supply of construction material as well as (especially) controlling costs. Our engineer friend Khun Sanguan is an "angel" for providing a lot of valuable advice.



29 December 2014